Abstract
Infill well drilling was planned and executed to increase production in a significantly depleted field. A total of 3 infill wells were drilled in 2 different layers of reservoir for an offshore operator in Myanmar. In the offset wells, water production had become significantly higher throughout. Previously all offset wells in this field were completed with open hole sand screens was chosen to isolate the water bearing sand in the sand reservoir below. Pore pressure prognosis were calculated from offset well depletion rate. Reservoir formation properties is assumed to be same throughout the field.
The first well was drilled and was found that there were two gas water contacts through the 3 targeted sand layers. The gas water contact and WUT (Water Up To) in this well were unexpected and it was prognosed that these gas water contact are there due to compartmentalization. The 7" liner were set and cemented throughout these reservoirs. The cement job went as per the plan and there were no losses recorded during cementing. However, initial cement log did not show isolation. 2 more runs of cement log were performed 6 days and 10 days later while conducting intervention activities on other wells. All three cement log came to the same conclusion, showing no isolation throughout the annulus of the 7" production liner. Significant amount of gas had percolated into the annulus over time. Despite no evidence of poor cement slurry design observed during running various sensitivity studies and post-job lab tests final cement log, which was conducted under pressure and confirmed no hydraulic isolation. A cement remedial job was planned and an investigation was conducted to identify the plausible root causes.
This paper explains on the root causes of poor cement presence in the annulus, and the remedial work that took place to rectify the issue.