Abstract
The paper discusses historical data related to downhole scaling, corrosion and surveillance methods to identify affected wells. Efforts to minimize production impact due to increased corrosion seen late in the field life along with longer term corrosion mitigation efforts are also reviewed. Examples of how tubing was originally protected by thin film scale accumulation and emulsion flow during early field life production are also presented. Increasing October's completion corrosion manageability is a key challenge facing the field. Addressing issues related to predicting future well failures and their associated production loss impact rig scheduling and procurement of expensive long-lead time completion material (Cr 13%).
The approved plan is to repair six wells per year over three years considering known well problems, remaining reserves, materials and rig availability. In early 2005, six well's were worked over and visual inspection of retrieved tubing showed an excellent match with caliper log data. The most severe corrosion is typically deep in the well and is related to high CO2 partial pressures. Corrosion risk to the casing has also been identified as potential issue and wall thickness assessments have been performed on some workovers. The paper reviews these items in greater detail and proposes forward plans for the remaining life of field.