This article studies the scheduling of block erection in shipbuilding. A mathematical model is formulated to minimize the make span, i.e., the time between the start and finish of the erection schedule, when there are different lifting and block joining times. Structural stability and the no-skipped-blocks property are taken as constraints. The model is used to study the erection in three special cases. First, the case with a short lifting time is analyzed. Second, a solution is constructed for the case in which joining times are short and, third, the case in which the lifting and joining times are the same is analyzed. The article shows how these three cases can be solved efficiently, and, in addition, it gives insight into the erection scheduling such as the effects of the number of blocks in the horizontal and vertical directions on different joining times.
Skip Nav Destination
Close
Article navigation
May 2013
May 01 2013
Block Erection Sequencing in Shipbuilding With General Lifting and Joining Times
Henri Tokola;
Henri Tokola
Aalto University School of Engineering
Search for other works by this author on:
Esko Niemi;
Esko Niemi
Aalto University School of Engineering
Search for other works by this author on:
Heikki Remes
Heikki Remes
Aalto University School of Engineering
Search for other works by this author on:
J Ship Prod Des 29 (02): 49–56.
Paper Number:
SNAME-JSPD-2013-29-2-49
Article history
Published Online:
May 01 2013
Citation
Tokola, Henri, Niemi, Esko, and Heikki Remes. "Block Erection Sequencing in Shipbuilding With General Lifting and Joining Times." J Ship Prod Des 29 (2013): 49–56. doi: https://doi.org/10.5957/jspd.2013.29.2.49
Download citation file:
Close
Sign in
Don't already have an account? Register
Personal Account
You could not be signed in. Please check your username and password and try again.
Pay-Per-View Access
$35.00
Advertisement
Cited By
Email Alerts
Advertisement
Suggested Reading
A Genetic Algorithm for Erection Scheduling at a Dock
J Ship Prod (February,2007)
Block Erection in the Event of Delays in Shipbuilding: A Scenario-Based Approach
J Ship Prod Des (February,2016)
A Group Technology Approach to Master Scheduling of Shipbuilding Projects
J Ship Prod (November,1989)
Resource-Constrained Shop-Level Scheduling in a Shipyard
J Ship Prod (May,2003)
A Heuristic Method to Schedule Pipe-Processing Flowshop in a Shipyard
J Ship Prod (November,2007)
Advertisement