Technology Update

A combination of new drill-bit technology and new operational practices has enabled operator Marathon Oil to use polycrystalline-diamond-compact (PDC) drill bits, and reduce drilling time by 24%, on wells in a part of the Anadarko basin where abrasive conditions at shallow depths previously have required the use of roller-cone bits.

Much of the Anadarko basin is dominated by PDC-bit drilling. However, in the southwest Canute area of Washita County, Oklahoma, the highly abrasive Granite Wash formation is encountered at depths of 5,000−6,000 ft, compared with its more typical 11,000-ft point of emergence in most of the Anadarko basin.

In the deep Anadarko, of which the southwest Canute area is a part, exploratory wells are drilled either to approximately 13,500 ft to produce the Atoka Wash and Red Fork sands or to approximately 17,500 ft to pro-duce the Morrow sands. The surface string in either type of well is set in or below the Brown dolomite formation (≈3,500−4,500 ft). The lithology below the surface casing consists of a long sequence of sand/shale with interbedded granite wash. This gives way to more-consolidated sand intervals and granite-wash formations, a transition often marked by the showing of the Tonkawa and Prue sands at approximately 9,000 and 11,000 ft, respectively.

In drilling Atoka Wash/Red Fork wells in the southwest Canute area, the operator set a goal of reaching the Prue sands by use of two PDC bits, eliminating the use of three to eight roller-cone bits that previously would have been required. Aggressive drilling parameters typically reserved for roller-cone bits, employing high weight on bit (WOB) and low revolutions per minute (rev/min), were combined with innovative PDC-bit frames, designed to increase the load/cutter ratio, and with new cutter technology to enable the operator to achieve the goal. A depth of 10,700 ft was reached with two PDC bits, and cost savings of approximately USD 200,000 were realized.

Well Plan

For the operator, a typical Atoka Wash/Red Fork well involves a 12.25-in. section drilled into the Brown dolomite and a 7.875-in. section then drilled to total depth (TD). For the 12.25-in. section, casing points differ according to TD. Typically, 9.625-in. casing is set at ≈3,500 ft. The 12.25-in. interval is easily drilled with a single PDC bit.

A 7.875-in. hole is drilled below the 9.625-in. casing and extends to TD. Historically, this interval has been drilled with multiple IADC 5–2–7 or 5–3–7 roller-cone bits. More recently, the use of PDC bits at drillout has become common. However, the ability to make the interval to the Prue sands has proved very elusive.

This content is only available via PDF.